Synergic

Synergic acquisitions are those acquisitions from different satellites over an Area of Interest that occur quasi-simultaneously, or with sufficient time vicinity.

The synergic constraint will remove "lone" acquisitions, keeping only the synergic ones, which are separated by a time distance lower than the defined maximum gap.

The following parameters are configurable

- Maximum gap: maximum allowed time distance between synergic acquisitions of different satellites

- Minimum cover: Minimum percent of common area covered by synergic acquisitions in relation to the target AOI. The common area covered is the intersection area of synergic swaths with the target AOI. If the minimum cover is set to 0 or negative, it will be ignored.

- Minimum area: Minimum area, in square kilometres, covered commonly by synergic acquisitions, measured as the common intersection between synergic swaths and the target AOI. If the minimum cover is set to 0 or negative, it will be ignored.

The synergic constraint applies to Areas of Interest only.

 

Synergic constraint disabled

Synergic constraint enabled, maximum gap = 20 minutes

 